| CLIENT: | Vuori |
| LOCATION: | Metairie, Louisiana |
| PROJECT TYPE: | Mall TI |
Permit Place recently completed permit expediting services for Vuori’s new mall tenant improvement in Metairie, Louisiana. The project involved an interior TI with storefront work in an interior mall, requiring coordination with the Jefferson Parish Department of Inspections and state fire authorities to secure plan check approval. As part of Vuori’s broader program rollout, maintaining schedule certainty was essential to their construction and opening timelines.
From initial plan intake through final approval, Permit Place managed the submittal, tracking, and communication process to ensure the TI permits were issued on time. The team focused on aligning Vuori’s construction schedule with Jefferson Parish’s review cycles and the state fire marshal’s requirements, delivering approvals three weeks ahead of the planned construction start.
Challenges
- Ongoing unclear communication from the Jefferson Parish Department of Inspections, with key interpretations and review expectations not consistently documented, requiring multiple follow-ups for clarification.
- State fire comments triggered a required resubmission, adding complexity and potential delay risk. Without tight coordination and rapid response, Vuori’s construction start could have easily slipped.
Solutions and Strategies
- Leveraged a robust Due Diligence process to anticipate submittal requirements and deliver a complete, clean initial application package.
- Implemented proactive communication measures: initiated regular check-ins, documented all feedback, and confirmed interpretations in writing with both the building department and state fire reviewers.
- Consolidated and expedited responses to state fire comments to minimize additional review time.
- Maintained transparency with Vuori’s program team by providing schedule forecasts and status updates tied to each review milestone.
Project Wins
- Approved in the first submittal round to the building department and received plan check approval 19 days after plans were received.
- Permits secured three weeks prior to the scheduled construction start, providing Vuori extra schedule cushion for contractor mobilization and material coordination.
- Demonstrated Permit Place’s ability to navigate inconsistent AHJ communication while protecting aggressive timelines, supporting Vuori’s brand expansion goals in the region.