Permit Place recently completed a multi-site rollout construction project for J. Crew. The project encompassed a 5,000 square foot space located in a bustling mall in Northbrook, IL.Â
This due diligence and permit expediting project involved securing approvals for building, mechanical, plumbing, electrical, and fire permits. We accomplished all of this in just 8 days.Â
During the initial phases of the project, our team encountered significant challenges, particularly with the local jurisdiction’s responsiveness. This lack of responsiveness raised concerns about potential delays during the review process.Â
Additionally, the building department’s hard-copy submittal requirement further complicated matters, introducing additional timelines for shipping and handling.
To navigate these hurdles, our team implemented a series of strategic measures. Foremost, we engaged directly with the jurisdiction to improve communication channels and response times.Â
Our due diligence process played a crucial role by ensuring all documents met local standards and requirements, helping avoid any unnecessary delays. This comprehensive approach was key in adjusting to the hard copy submissions and ensuring all materials were correctly formatted and presented.
While the estimated permit turnaround time was initially set at 6 weeks, our efficient handling and expediting efforts dramatically reduced this to just 1 week.Â
The project received approval in the first submission round, and the review process took only 8 business days. Consequently, J. Crew had their permit in hand a full month before the scheduled start of construction.
The success of the J. Crew multi-site rollout in Northbrook, IL stands as a testament to Permit Place’s expertise in navigating complex permit processes with efficiency and precision. Our proactive strategies and meticulous planning ensured that even with initial challenges, the project not only met but exceeded expectations, reinforcing our commitment to client success in the retail construction sector.