Stonestown Galleria Tenant Improvement Permits: What You Need to Know
By Permit Place | Last updated: February 2026
Tenant improvement permits at Stonestown Galleria require approval from Brookfield Properties and submission to the San Francisco Department of Building Inspection (DBI). Expect 12 to 16 week plan review for TI projects. Brookfield coordinates tenant approvals through their in-house tenant coordination team.
Stonestown Galleria is a regional shopping center undergoing redevelopment in San Francisco, California. The property is owned by Brookfield Properties, one of the largest commercial real estate owners in North America. If you are planning a tenant improvement at Stonestown Galleria, understanding San Francisco’s notoriously slow permit process is critical.
San Francisco has some of the longest permit review times in the United States. Plan on 12 to 16 weeks for standard TI projects, longer if your project triggers health department review or change of occupancy. Brookfield’s in-house tenant coordination team helps expedite the landlord approval side, but the city timeline is outside their control.
About Stonestown Galleria
Stonestown Galleria is a regional shopping center undergoing redevelopment owned by Brookfield Properties. The property is located in San Francisco, California.
Stonestown Galleria is undergoing a $2 billion mixed-use redevelopment that will add approximately 3,500 residential units, new retail, and community space. Existing tenants face evolving permit requirements during the phased construction. Coordinate early with Brookfield if your TI project overlaps with redevelopment phases.
The TI Permit Process at Stonestown Galleria
Tenant improvement permits at Stonestown Galleria follow a five-step process. Each step is required. Skipping any step will delay your project.
- Landlord Letter of Authorization from Brookfield Properties’ tenant coordination team. Before you can apply for a city permit, you need written authorization from Brookfield Properties. The tenant coordination team reviews your construction plans to verify they meet building standards and do not interfere with building systems. This approval typically takes 1 to 2 weeks after you submit complete plans.
- Architectural plans meeting Brookfield Properties’ design standards. Your architect must prepare construction drawings that comply with Brookfield’s tenant design criteria. These standards cover partition wall construction, fire-rated assemblies, electrical and plumbing connections, HVAC tie-ins, and fire protection system modifications. Brookfield will reject incomplete or non-compliant plans.
- Submit to San Francisco Department of Building Inspection for plan review. Once Brookfield approves your plans and provides the landlord authorization letter, you submit your permit application to the San Francisco DBI. San Francisco permits are submitted through the city’s online portal or in person at the permit center. You will need the building permit application, all construction drawings, energy calculations, and the landlord authorization letter.
- Address city comments and corrections. San Francisco DBI plan checkers review your drawings for compliance with the California Building Code, California Fire Code, and San Francisco-specific amendments. Most TI projects receive correction comments after the first review. Your architect addresses each comment, revises the drawings, and resubmits. The backcheck review typically takes 15 to 25 business days.
- Permit issuance and construction start. After San Francisco DBI approves all plans, the city issues your permit. You pay the remaining permit fees, post the permit at the job site, and construction can begin. DBI building inspectors will visit the site at required milestones during construction.
What’s Happening at Stonestown Galleria
Stonestown Galleria is undergoing a $2 billion mixed-use redevelopment that will add approximately 3,500 residential units, new retail, and community space. Existing tenants face evolving permit requirements during the phased construction. Coordinate early with Brookfield if your TI project overlaps with redevelopment phases.
Jurisdiction Requirements
Stonestown Galleria is located in San Francisco, California, which means all building permits are handled by the San Francisco Department of Building Inspection (DBI). San Francisco has some of the slowest permit review times in the United States.
San Francisco processes commercial tenant improvement permits with typical first-round review times of 30 to 60 business days for standard retail and restaurant TI projects. Expect 12 to 16 week plan review for TI projects. Restaurant and change-of-use projects often take longer due to health department and fire marshal reviews.
Brookfield Properties coordinates tenant approvals through their in-house tenant coordination team. This team manages the landlord side efficiently, but the San Francisco permit timeline is outside their control.
For more information on San Francisco building permits, review times, and submittal requirements, see our full permit guide for San Francisco, CA.
FAQ
What permits do I need for a tenant improvement at Stonestown Galleria?
Most TI projects at Stonestown Galleria require a building permit, electrical permit, plumbing permit, mechanical permit, and fire protection permit. The specific permits depend on the scope of your work. Interior wall construction, new electrical circuits, plumbing fixtures, HVAC modifications, or fire sprinkler relocations all trigger permit requirements. Contact the San Francisco Department of Building Inspection or a permit expediter to confirm which permits your project needs.
How long does the TI permit process take at Stonestown Galleria?
The full TI permit process at Stonestown Galleria typically takes 14 to 20 weeks from application to permit issuance. This includes 1 to 2 weeks for Brookfield Properties landlord approval, 30 to 60 business days for the first round of San Francisco DBI plan review, and 15 to 25 business days for backcheck after corrections. Projects with incomplete submissions or multiple correction rounds take longer.
Do I need landlord approval before applying for a permit?
Yes. Brookfield Properties must review and approve your construction plans before you can submit a permit application to the San Francisco DBI. The DBI requires a signed landlord authorization letter from Brookfield Properties with your permit application. Submitting without this letter will result in an intake rejection.
What is a Landlord Letter of Authorization?
A Landlord Letter of Authorization is a signed letter from the property owner (in this case, Brookfield Properties) that gives you permission to perform construction work in the leased space and to apply for building permits on their behalf. The San Francisco DBI requires this letter for all tenant improvement projects. You obtain it from Brookfield’s tenant coordination team after they approve your construction plans.
How can Permit Place help with permits at Stonestown Galleria?
Permit Place expedites tenant improvement permits at Stonestown Galleria by coordinating with Brookfield Properties’ tenant coordination team, preparing complete permit applications that avoid intake rejections, submitting to the San Francisco Department of Building Inspection, tracking review status daily, and turning around correction responses within 24 to 48 hours. We handle the entire process from landlord approval through certificate of occupancy so your buildout stays on schedule.