Sahuarita Town, AZ Building Permits: Review Times, Process and Costs
By Permit Place | Last updated: February 2026
Sahuarita Town, AZ building permit timeline: Plan review takes 5 to 21 days depending on project type. Contact the building department for current processing times.
Building permit review in Sahuarita Town, AZ typically takes between 5 and 21 days depending on project type and complexity. This page covers review timelines, required permits, costs, and how to speed up the process.
Sahuarita Town Plan Review Timeline
- General Review Timeframe Policy in Sahuarita, AZ
- The Planning & Building Department follows a Review Timeframe Policy to comply with Arizona’s Regulatory Bill of Rights (A.R.S. Title 9, Chapter 7, Article 4).
- The Department allows for an administrative review of application completeness and two substantive reviews for compliance.
- If the applicant makes significant changes not in response to a correction request, an additional comprehensive request for corrections is allowed.
- After these substantive reviews, the application must be approved or denied.
- The law requires the publishing of processing timeframes, but specific days for “first submittal” and “subsequent submittals” are not explicitly defined in the main Review Timeframe Policy document.
- Design Review Processing for Sahuarita, AZ
- Design Review Applications:
- The planning and building director or designee shall review each application for completeness within five working days.
- Once an application is accepted as complete, the town will review it within 15 working days.
- Design Review Applications:
- Exemptions
- Applications or permits issued within seven working days or expiring within 21 days are exempt (e.g., zoning clearances, certain home occupation and sign clearances).
- Licenses for permits related to residential lot construction (swimming pools, hardscape, property walls, residential subdivisions, master planned communities) are also exempt.
- Summary of Key Timing
- Administrative/Completeness Review: 5 working days for design review applications (to determine if application is complete).
- Substantive Review (after completeness): 15 working days for design review applications.
- Subsequent Reviews: Not explicitly stated in general policy for standard building permits. If additional information is needed due to corrections or changes, this may result in additional review cycles, but durations for subsequent reviews are not specified.
- Zoning, Home Occupation, and Sign Clearances: Issued within 7 working days if they do not require a building permit.
No explicit, department-wide timeframes for "first submittal" and "subsequent submittals" of general building permit plan checks are published beyond the above design review process and exemptions. For design review, the framework is clear: 5 days for completeness, 15 days for review after being accepted as complete. For all other building permits, only the exemptions and general process are described—not specific timeframes for standard plan reviews.
Last verified: June 2025 | Source: Sahuarita Town Building Department
Need it faster? Permit Place can expedite your Sahuarita Town permits
What Building Permits Do You Need in Sahuarita Town?
Sahuarita Town requires permits for most construction activity. The type of permit depends on your project scope.
Commercial Permits
- New commercial construction: full plan review with the longest timeline
- Tenant improvements and interior buildouts: plan review for structural, electrical, plumbing, and mechanical changes
- Change of use: required when converting building use (for example, retail to restaurant)
- Shell and core: separate from tenant improvement permits
Residential Permits
- New home construction: full plan review including structural, mechanical, electrical, and plumbing
- Additions and remodels: required when modifying structure or adding square footage
- Decks, pools, fences: separate permits with typically faster review
Trade Permits
Individual trade permits are typically required for electrical, plumbing, mechanical (HVAC), and fire sprinkler work.
How the Sahuarita Town Permit Review Process Works
Step 1: Application Submission
Submit your permit application through the Sahuarita Town building department. Applications are reviewed for completeness before being assigned to a plan reviewer.
Step 2: Plan Review
The city reviews your submitted plans for building code compliance, structural integrity, fire safety, energy code, and ADA accessibility. Commercial projects are reviewed by multiple departments at the same time.
Step 3: Corrections and Resubmittal
If the city issues correction comments, you will need to revise your plans and resubmit. Each correction cycle adds another review period. Most commercial projects go through 2 to 3 correction cycles.
Step 4: Permit Issuance
Once all review departments approve your plans, the building permit is issued. Schedule inspections as work progresses.
Note: These timelines reflect general review periods. Large or complex projects may take longer. Request a quote from Permit Place for a project-specific estimate, or get an instant due diligence report from PermitNow.io.
Sahuarita Town Building Permit Costs
Permit fees in Sahuarita Town vary based on project type and valuation.
Commercial
- Tenant improvements: $500 to $5,000+
- New commercial construction: $2,000 to $25,000+ (based on valuation)
- Plan review fee: typically 50-65% of the building permit fee
Residential
- Small projects (decks, pools, fences): $50 to $300
- Home additions and remodels: $200 to $2,000+
- New home construction: $1,000 to $10,000+ (based on valuation)
For a detailed permit cost breakdown specific to your project, get a free due diligence report from PermitNow.io.
Trade Permits
- Electrical: $50 to $500
- Plumbing: $50 to $500
- Mechanical: $50 to $500
Fee ranges are estimates. Actual fees depend on project valuation and scope. Contact the Sahuarita Town building department or Permit Place for exact costs.
Sahuarita Town Building Department
Sahuarita Town Building Department
- Website: sahuaritaaz.gov/754/Community-Development
- City Website: sahuaritaaz.gov
Frequently Asked Questions About Sahuarita Town Building Permits
How long does it take to get a building permit in Sahuarita Town?
Plan review in Sahuarita Town, AZ takes 5 to 21 days for the initial review cycle. Projects that receive correction comments will need additional review cycles, each adding time to the total. Most commercial projects go through at least two review cycles before approval.
What is the difference between residential and commercial permit review in Sahuarita Town?
Commercial projects in Sahuarita Town require review by multiple departments (building, fire, public works, and sometimes health), which adds time. Residential projects typically involve fewer review disciplines and can be processed faster. Tenant improvements fall between the two depending on scope.
Can I speed up the permit process in Sahuarita Town?
The most effective way to speed up the permit process in Sahuarita Town is to submit complete, code-compliant plans on the first attempt. This reduces correction cycles, which are the primary cause of delays. Permit Place helps ensure your application is complete before submission.
Do I need a permit for a tenant improvement in Sahuarita Town?
Yes. Most interior buildouts in Sahuarita Town that involve structural changes, electrical work, plumbing, or HVAC modifications require a building permit. Simple cosmetic changes (paint, flooring, non-structural work) typically do not require a permit.
How much does a building permit cost in Sahuarita Town?
Permit fees in Sahuarita Town are calculated based on project valuation and type. Commercial projects typically pay $500 to $25,000+ in total permit and plan review fees. The exact cost depends on project scope, square footage, and any additional trade permits required.
Can a permit expediter help with my Sahuarita Town project?
Yes. Permit Place expedites building permits in Sahuarita Town and 600+ other jurisdictions. We handle everything from application preparation through plan review, corrections, and permit issuance. Our clients typically get permits faster because we submit complete applications that reduce correction cycles.
What building permits do I need in Sahuarita Town, AZ?
Most construction in Sahuarita Town requires a building permit. This includes new construction, tenant improvements, change of use, additions, and major renovations. Separate trade permits for electrical, plumbing, mechanical, and fire protection are also typically required. For a project-specific permit requirements report, use PermitNow.io.
Permit Review Times in Other Arizona Cities
Need Help With Sahuarita Town Building Permits?
Permit Place has helped hundreds of businesses get permits in Sahuarita Town and across Arizona. We handle everything from application to approval so you can focus on building.
Request a Free Quote
Free DD Report
Want to know exactly what permits your project needs? Get an instant due diligence report from PermitNow.io. View a free demo DD report