A Building Permits Does Not Guarantee Occupancy

 Just because your plans have been approved by the jurisdiction, your building permits have been issued and you have completed the construction of your project does not mean it will meet all the necessary life safety requirements to get your certificate of occupancy.
One client had installed 43 4 ft x 8 ft heat and smoke dampers on the roof. The factory approves specifications for the smoke dampers earlier by the city Fire Marshal.

Some building permits do not mean occupancy. Not ready for use, but it does allow construction to begin. Meeting safety and code requirements same time as it is under construction and afterward determining occupancy. The building cannot be legally occupied without final approval.

Building Permits Alone Doesn’t Ensure You Can Move In:

That isn’t all it takes, the building permit is just one step. Inspect the work at different points to check that it meets local codes. The Certificate of Occupancy is not issued if issues are found. It assures the building is safe to be used.

Many factors cause a delay in occupancy. Setbacks can occur if you fail inspections, don’t do the work, or don’t submit paperwork. If you stay in touch with inspectors and follow their guidance, you will avoid delays. Clear planning and communication are good at managing your project.

Building permits are just the beginning; the finish line is the Certificate of Occupancy, which proves that the building is safe and complies with all requirements. Make sure that all steps are always focused so that the transition from construction to occupancy is smooth.

During the final inspection, the Fire Marshal realized the smoke dampers did not meet the 1997 Uniform Fire Code requirements.

Even after several attempts to negotiate an inexpensive solution, the dampers had to be replaced, which cost the contractor considerable money.

The owner felt the contractor and architect should have been aware of what are the requirements to meet the current code. That was a tough lesson!

Schedule Time to Talk