Permit Place helped Burger Lounge get building permits in San Diego, CA.
Approvals 1 month early
The project involved a major renovation, requiring the acquisition of multiple permits, including Building, Mechanical, Plumbing, Electrical, Fire, and Health.
Development in the City of San Diego is booming, often resulting in elongated permit review times. This can pose a significant challenge to businesses with tight construction deadlines.Â
The Burger Lounge permitting project also had an inherent hurdle. Due to project timing, the permit applications were submitted during the holiday season, when plan check staff availability is limited. Â
Because of these factors, we forecasted a turnaround time of 4.5 months for permit approvals.
Thanks largely to our team’s familiarity with San Diego restaurant permitting and the building department’s permit requirements, we managed to secure all necessary permits in just 3.5 months – a whole month ahead of our initial estimate.
This expedited approval was a monumental win, ensuring that Burger Lounge’s construction schedule remained on track.
We delivered for Burger Lounge here. Permit Place has expedited commercial building permits in 600+ cities since 2003.
Building permits in San Diego? See our full guide: San Diego Building Permits: Review Times, Fees & Process
More California permit guides:
Learn more about commercial permitting:
Let’s schedule 30 minutes to discuss your project and how Permit Place can help make the permit approval process easier.